whiteprop.gif (1400 bytes)




prop2.gif (5070 bytes)

press.gif (1624 bytes)

prop2.gif (5070 bytes)

 

Nordex N29/250 further improves the clean image of King Island.

Following a successful tender application, the Hydro-Electric Corporation a subsidiary of Tasmania’s government, Australia’s most southerly state, Sterling Wind Pty Ltd, Nordex Balke Dürrs, Australian agents, were contracted to supply and erect 3 X N29 250 kW. Nordex Balcke-Dürr Wind Turbines on 30 m. tubular towers for King Island, a 64 kilometre by 27 kilometre remote Island 80 kilometres from the Australian south coast.

King Island is a popular tourist destination, and its well known for its fresh produce, being beef, dairy products, fishing and special bottled rain waters. The three Windturbines have now added to King Island’s clean environment image, and become the latest tourist attraction on the Island.

Because of the Islands remoteness and fragile environment, it was extremely important that strict control over environmental standards was maintained by the Hydro Electric Corporation and Sterling Wind during construction, the H.E.C. have been carefully planing the Windturbine site to ensure the Windturbines visually would blend into the landscape and minimise the disturbance and impact of the environment.

The Windturbines were manufactured by Nordex Balcke-Dürr GmbH in Denmark, they were shipped from Europe to Melbourne in five 40-foot containers and one 20-foot containers.

In Melbourne the containers were loaded on to semitrailers and had to be ferried to the Island, via mainland Tasmania. including a 100 tonne Demag mobile crane for unloading, assembly and erection of the equipment

The time schedule was very tight as the mobile crane and the semitrailers with the containers had to be ready for return shipping to Melbourne within six days, which allowed only two days for unloading, assembly and erection of each Windturbine.

Due to the remoteness and the harsh wind conditions on the island the working conditions, were very difficult with sand storm where the soil had been disturbed, However, the three Windturbines were all pre-assembled on the ground, ready for erection five days after the equipment’s arrival to the island, on the sixth day all three windturbines were erected.

Finally, the Windturbines were successfully commissioned on the January 23rd 1998 after the Christmas and New Year holidays. After three (3) months of operating the Windturbines have been running remarkably well and generated over 500,000 kW/h. in total.

The PLC controlled SCR. triggered Wind/Diesel control including a special Dump load system was designed by Sterling Wind and T~Tech and manufactured by T~Tech, an Australian Consulting and Engineering a company specialising in Power Electronic and diesel power generation controls.

The dumpload is connected to the low voltage part of the Wind Farm feeder:

The dumpload consists of four heating elements ( 35 kW. - 70 kW- 140 kW - 280 kW.) mounted in a cabinet, cooled by fans. The dumpload can be controlled in steps of 35 kW from 0 to 525 kW.

The heating elements are switched on/off by solid state switches at zero crossing. This enables the dumpload to change it’s load very fast (once every 20 m/sec). As the solid state switches are fully electronic, their lifetime is much longer than any mechanical moving device.

The solid state switches are controlled via digital outputs of a dedicated PLC. communicating with the Diesel Power Station Controller providing optimal power level from the Wind Farm. The same PLC will turn On and Off Windturbines as required for regulation.

The control system is expandable up to 100% of wind power generation using the same strategy and equipment with future additions of more Windturbines where the system can run with all Diesel power shut down, with this existing system it has been proved during commissioning that the system can operate with at least 85% of the energy from wind power, with the system still being stabile, including Voltage and Frequency.

The active power output from the wind park is controlled by start/stop of one or more wind turbines and by switching heating elements in the dumpload on/off. The dumpload can be controlled in steps of 35 kW. from 0 to 525 kW.

The set point for the primary (relatively slow) controller in the cascade control loop for active power can be either:-

1. A maximum wind park output, set by the diesel power plant operator, or

2. Calculated on the basis of a percentage of penetration, set by the diesel power plant operator, or

3. Calculated on the basis of a percentage minimum load on the diesel(s) in operation, set by the diesel power plant operator. This method has been used successfully in previously, or

4. Calculated in a mathematical model, based upon more of the above parameters.

The set point for the secondary (fast) controller will be the present wind park output. This will largely minimise the consequence of fluctuating wind power.

When the dumpload is unable to keep the output down at the set point, a wind turbine is stopped. The turbine to be stopped will always be the one with the highest number of hours in operation.

When the start wind is achieved at more than one Windturbines at the same time, the control system sends the start signals to the turbines with a delay of one minute between each start.

An operator initiated stop (chosen from the power plant control system) overrules the wind park control system and must be reset from the diesel power plant before the turbines can be started.

When the active power is controlled as suggested above, utilisation of the available wind power can be pushed to a high limit without endangering the integrity and power quality of the grid.

It should be noted that especially on small, weak grids, stall controlled wind turbines with dumpload control are superior to pitch controlled turbines.

1. The dumpload control is much faster than the pitch control and therefore, able to ease the influence of fluctuating wind conditions when using a stall regulated Windturbine.

The PLC is connected to the diesel power plant’s PC. though optical fibre serial communication link.

Control of the relevant digital signals (circuit breaker status, etc.) from the diesel power plant (via digital inputs or RS 232C).

The control system is expandable for more than 100% future additions.

CONTROL SYSTEM SOFTWARE

The software is divided into the following three groups:-

PLC Logic Control Software.

1.The software is s programmed in logic ladder program. It controls the dumpload unit.

2.Start/stop of the wind turbines.

3.Monitoring various grid feeder and Diesel Station Load.

The control systems enables the fully automatic operation of the Windturbines in parallel with the Hydros existing diesel power station, which was build and commissioned in 1985 and is well maintained in excellent operating condition and appearance. It is fully automatic, capable of operating unattended for periods up to 48 hours.

Existing Diesel Power Station And Facilities.

Four (4) X 1200 kW. diesel generators with unit transformers, operating at 1500 rpm. And in parallel connection to the Diesel Power Station’s 11 kV. Bus. Varying demands result in operating loads ranging from a night time minimum of 850 kW. to a day time maximum of 2700 kW. controls are fully programmable and logic schedules as follows:

System Load: Operating Generators:

Load < 1100 kW. 1200 kW. (1 X 1200)

1100 < Load < 2200 kW. 2400 kW. (2 X 1200)

Load > 2200 kW. 3600 kW. (3 X 1200)

With the average annual wind speed of 9.5 m/Sec. the site is exposed to the "roaring 40s" that are predominantly westerly winds making King Island one of the best wind regime areas in Australia.

Estimated power generated by this project of 3,000,000 kW/h. annually, enabling savings in diesel costs of A$500,000.00 per year.

Further reduction in maintenance and overhaul cost of diesel generators are achieved by reduced operating hours, where at times one diesel generator can be shut down due to high generation from the wind farm.

The wind farm will supply 20% of the Islands power needs, and it is expected that further equipment will be required from the H.E.C. to increase the size of wind farm for further reduction in diesel fuel consumption.

Back to Press Contents Top of Page

 

© Sterling Wind Pty. Ltd. 1998. Web Site by Creation Online Services. Send email about this site to info@wind.com.au.